Research note  ·  June 2026

The Capex Cycle:
Telecom 2000 vs. AI 2026

A side by side look at two of the largest capital build-outs in modern markets. We set the late 1990s telecom and fiber cycle against today's build-out of artificial intelligence and data centers, with the underlying data for each, so the comparison rests on evidence rather than narrative.

Series
Research note
As of
June 2026
Coverage
Capex, power, credit
Funding
Today's build-out is paid for mostly from operating cash flow, not debt
Assets
The costly hardware is a larger, shorter lived share of cost than fiber was
Concentration
The ten largest S&P 500 firms are a record share of the index

Executive Summary

Two build-outs, set side by side

The fiber thesis of 2000 turned out to be right, and the cables were eventually used. Even so, nine of the ten largest companies in the world at that peak went on to trail the index for the next 25 years, and the Nasdaq did not pass its March 2000 high again until 2015. That gap between a correct idea and a profitable investment is the reason this comparison is worth drawing carefully.

On structure, the two cycles resemble each other. Both pair a major new technology with capital spending measured in the hundreds of billions a year. Both rest, at least in part, on demand forecasts that run ahead of current revenue. Both involve financing that loops between suppliers and customers. And in both, the assumptions about how fast the equipment wears out have a real effect on reported profit. Judged on structure alone, the present cycle can look like a repeat of the last one.

On substance, several differences stand out, and they point the other way. The telecom carriers funded their networks with debt raised against earnings that were, in the most serious cases, fabricated. Today's large platform companies fund most of their spending from established, cash generative businesses and hold net cash rather than net debt. AI usage is visible in reported revenue and in metrics like tokens processed, where the 2000 demand projections never showed up in the numbers. And the depreciation question today concerns disclosed estimates, not the fraud that defined WorldCom, Qwest, and Global Crossing.

The newer questions sit at the edges of the system rather than at its center. Electricity has become the practical limit on how fast data centers can be built, a constraint that barely existed in 2000. A growing share of the financing is moving into private credit and off balance sheet vehicles, where it is harder to see. And one structural fact applies to passive and active investors alike: the ten largest companies now make up a record share of the S&P 500. None of this is presented as a prediction. The aim is to lay out the evidence on both sides, identify the specific things worth monitoring, and let you weigh them.

~$120B
Peak US telecom capex in 2000, about $213B in today's dollars1
$448B
Combined large platform capex in 2025, up from $162B in 20228
78%
Nasdaq decline from its 2000 peak to the 2002 low6
15 yrs
Time for the Nasdaq to return to its 2000 high
1 of 10
Of the 2000 top ten, the number that beat the S&P over 25 years7
40.7%
Share of the S&P 500 in its ten largest firms, a record19

At A Glance

Same, similar, or different, line by line

Nine points of comparison, each marked for how closely this cycle tracks the last. The shorthand is simple: same the pattern repeats, similar it broadly resembles 2000, different it has genuinely changed from the last cycle, and new it has no real precedent in 2000.

Dimension
Telecom, 2000
AI, 2026
Read
Capital intensity
Roughly $120B at the peak, heavily concentrated in the US
About $448B in 2025 across the large platforms, and global
similar
Funding source
Debt and high yield issuance, against weak or false earnings
Mostly operating cash flow, on net cash balance sheets
different
Demand evidence
Projected traffic that did not arrive on schedule
Visible in revenue and usage, though spending still leads
different
Circular financing
Vendor loans from Lucent, Nortel, and Cisco to buyers
Cross investment among chip makers, model labs, and clouds
same
Asset life
Fiber stayed useful for decades
Leading chips are refreshed every two to three years
different
Power demand
Modest, not a limiting factor
A central constraint on the pace of the build-out
new
Off balance sheet
Some structured and vendor financing
Growing use of private credit and special purpose vehicles
similar
Index concentration
Top ten near 27% of the S&P 500
Top ten at a record 40.7%
similar
Leadership durability
Most 2000 leaders never recovered their highs
Unsettled, and the central open question
watch

The pattern that follows: funding and demand are differences that lower systemic risk relative to 2000. Asset life is also a difference, and it runs the other way, since the hardware must be earned back far faster than fiber did. Circular financing is a genuine parallel to 2000, while capital intensity, off balance sheet leverage, and concentration are broadly similar. Power is genuinely new. Each is taken in turn below.

Part I  ·  The Precedent

The telecom build-out and the downturn that followed

To judge the present cycle, it helps to recall in detail what the last one actually looked like, since it is now often remembered only in summary.

The spend, and the capital behind it

Through the second half of the 1990s, US investment in communications equipment rose from roughly $62 billion a year in 1996 to more than $135 billion by 2000 in constant dollars, a pace of nearly 18% a year.1 Total telecom capital spending peaked near $120 billion in 2000. The Telecommunications Act of 1996 had opened local markets to competition, and capital flowed in to build the networks that competition was expected to need. Much of that money was borrowed. The share of US high yield bond issuance coming from telecom climbed from about 15% in 1997 toward half of the market by 2000, and a generation of new long distance and competitive local carriers funded fiber routes with debt raised against business plans rather than customers.

US communications equipment investment
Constant 1996 dollars
Spending more than doubled in four years before the cycle turned.
Source. Federal Reserve Bank of Richmond, Boom and Bust in Telecommunications, 2003. Figures are investment in communications equipment in constant 1996 dollars, a series distinct from total nominal telecom capex, which peaked near $120B in 2000.1

How capital spending inflated reported earnings

The mechanism that turned heavy network investment into a solvency problem is worth stating plainly, because a version of it recurs today. When a company builds a network, the cash goes out at once but the cost is spread across the asset's expected life through depreciation. The longer the assumed life, the smaller each year's charge, and the larger reported earnings look in the meantime. Pair generous asset lives with heavy borrowing and a company can report growing operating earnings while consuming cash and adding debt. That worked while capital was available. It stopped working the moment funding tightened.

The demand forecast that did not arrive

The build-out was justified by a widely repeated claim that internet traffic was doubling every hundred days, an annual rate near 1,000%. The figure originated with a single carrier's marketing in the late 1990s and was repeated in industry and government reports until it was treated as fact. Independent measurement by the researcher Andrew Odlyzko found that traffic was in truth roughly doubling each year, fast, but closer to 70 to 150% than to 1,000%.4 Networks had been sized for the larger number. When demand grew at the smaller one, the result was a vast surplus of unused capacity.

The demand forecast versus measured traffic
Cumulative growth, log scale
A claim of doubling every hundred days against the reality of roughly doubling each year.
A logarithmic axis is used so both paths remain visible. After three years the marketing figure implies about a billion fold increase, the measured figure about eightfold. Source. A. Odlyzko, Internet traffic growth, sources and implications.4

The surplus, the failures, and the losses

By the early 2000s more than 80 million miles of fiber had been laid in the United States, and industry estimates suggest the large majority of it sat unlit for years, since precise figures were never knowable.5 Prices for long haul capacity fell sharply, by some measures around 90%. As funding markets closed, the carriers that had borrowed against projected traffic could not service their debt. The failures that followed were among the largest of the era, and several involved accounting fraud rather than only optimism.

The accounting failures, in brief

WorldCom moved more than $3.8 billion of ordinary operating costs into capital accounts, which both inflated profit and overstated assets by over $11 billion, and filed for bankruptcy in July 2002 with about $104 billion in assets and $41 billion in debt.2 Global Crossing filed in January 2002 with roughly $22.4 billion in assets against $12.4 billion in debt.3 Qwest later restated billions in improperly recognized revenue. These were failures of integrity, not only of forecasting, and that distinction matters when comparing the era to today.

Vendor financing, the demand the sellers paid for

One feature of the period has a direct parallel now. The equipment makers helped their customers buy the equipment. Lucent extended about $8.1 billion in financing commitments to buyers, Nortel about $3.1 billion, and Cisco about $2.4 billion, with industry commitments reaching perhaps $25 to $33 billion by late 2000.4 When a supplier lends a customer the money to buy its product, the resulting sale is real on the income statement but the demand behind it is partly the supplier's own capital returning as revenue. That made end demand look stronger than it was, and it is the cleanest precedent for the cross investment in today's market.

Vendor financing commitments, 2000
$ billions
Equipment makers funding their own customers.
Approximate committed amounts. Suppliers recorded sales while effectively lending buyers the purchase price, a structure that overstated the strength of end demand.4

The takeaway

The telecom downturn was not caused by a bad idea. Fiber was genuinely valuable and is in heavy use today. It was caused by borrowing against earnings that depended on demand that had been overstated, in several cases through outright fraud, while the assets were funded with debt that demand could not service.

Part II  ·  The Aftermath

A right idea, and the wrong stocks

The most useful lesson from 2000 is not that the technology disappointed. It is that being correct about the technology did not protect investors who owned the leaders at the peak. This is the part of the history most worth holding in mind.

The index, a fifteen year round trip

The Nasdaq Composite closed at 5,048.62 on March 10, 2000. It bottomed at 1,114.11 on October 9, 2002, a decline of 78%, and did not close above its 2000 high again until April 23, 2015, roughly fifteen years later.6 Adjusted for inflation, an investor who bought the index at the peak was still behind well into the following decade. The broad market fared better than the Nasdaq but still produced what is often called a lost decade, with the S&P 500 returning close to zero on a price basis over the ten years from 2000.11

Nasdaq Composite, peak to recovery
Index level
From the March 2000 high to the October 2002 low, and back, over fifteen years.
Source. Dow Jones Market Data and Reuters. Closing values on the dates shown. The 2002 low is a closing figure.6

The individual outcomes

The index figures understate what happened to the companies most associated with the build-out. Cisco, the most valuable company in the world for a time in 2000, fell about 89% from its high and did not reclaim that price until December 2025, more than a quarter century later. Intel did not exceed its 2000 high until 2026. Nortel, worth roughly $398 billion at its peak and about 38% of the value of the entire Toronto exchange, filed for bankruptcy in 2009. JDS Uniphase fell more than 99%. The equipment that these companies built proved its worth. The equity did not follow.

The largest companies, twenty five years on

Consider the ten largest US companies at the 2000 peak and how their stock performed against the S&P 500 over the following 25 years. By common measures only one, Microsoft, outpaced the index, and even Microsoft spent more than a decade below its 2000 level before its later software and cloud businesses carried it past.7

1
Microsoft
Recovered after roughly fourteen years, then led on cloud
beat index
2
General Electric
Trailed for the period, later split into separate companies
trailed
3
Cisco Systems
Down about 89%, regained its high only in 2025
trailed
4
Intel
Exceeded its 2000 high only in 2026
trailed
5
Walmart
Steady operator, roughly tracked the index
in line
6
ExxonMobil
Energy cycles drove returns, broadly in line over the span
in line
7
Lucent
Absorbed into Alcatel then Nokia after steep losses
trailed
8
IBM
Long stretch of flat returns relative to the index
trailed
9
Citigroup
Severely impaired in the 2008 financial crisis
trailed
10
AIG
Required a government rescue in 2008
trailed

Constituents and outcomes compiled from multiple public sources; per name 25 year returns are estimates and the ranking varies slightly by date and method. The pattern, not any single figure, is the point.7

Owning the technology and owning its current leaders were not the same decision in 2000, and the difference compounded for a very long time.

The takeaway

A correct view of where technology is heading does not, by itself, identify which companies will capture the value or what price is reasonable to pay for them. The fiber thesis was right. Most of the equities that expressed it were not the way to own it. That is the single most transferable lesson from the last cycle to this one.

Part III  ·  The Present Cycle

The AI build-out, larger spending on stronger balance sheets

The present cycle is bigger than 2000 in dollar terms and is being funded very differently. Both facts matter, and they pull in opposite directions, which is why a single label does not fit.

The scale

Combined capital spending by the largest platform companies rose from about $162 billion in 2022 to roughly $448 billion in 2025, a figure that includes the cloud build-out at Amazon, Microsoft, Alphabet, Meta, and Oracle.8 Estimates for 2026 are higher still, generally in the six hundred billion dollar range, though these are forecasts and depend on definitions. Measured against the roughly $120 billion that the entire US telecom industry spent at its 2000 peak, several of these companies are now individually approaching or exceeding that figure. The absolute numbers are without precedent in corporate history.

Capital spending, telecom peak versus platforms
$ billions
The 2026 figure is an estimate; the rest are reported.
Telecom is the approximate 2000 industry peak. Platform figures are combined capex for Amazon, Microsoft, Alphabet, Meta, and Oracle. Source. Epoch AI, parsed from filings; 2026 is a consensus estimate and varies by source.8

Who is paying, the decisive difference

The most important contrast with 2000 is not the size of the spending but the balance sheets behind it. The telecom carriers borrowed to build, against earnings that in the worst cases were not real. The large platforms today fund the majority of their capital spending out of the cash flow of established, highly profitable businesses, and most hold more cash than debt. That single difference is the strongest reason a synchronized, debt driven downturn of the kind seen in 2000 is less likely now. It does not remove every risk, as later sections show, but it changes the base case materially.

Estimated 2026 capital spending by company
$ billions, estimate
Individual budgets that approach or exceed the entire 2000 telecom peak.
Figures are 2026 estimates that blend company guidance and analyst forecasts, and definitions vary, for example fiscal versus calendar year and the treatment of leased capacity. Treat as approximate.9

Spending relative to revenue

A useful way to size the commitment is capital spending as a share of revenue. On 2026 estimates this ranges from about a quarter of revenue at Amazon to the mid forties for Microsoft and Alphabet, to more than half at Meta, to the mid eighties at Oracle.10 These are high figures by any historical standard for companies of this size, and they are the clearest sign that the firms regard the opportunity as large. They are also the reason free cash flow has come under pressure even at very profitable businesses.

Capital spending as a share of revenue, 2026 estimate
Percent of revenue
A measure of how much of the business is being reinvested into the build-out.
Source. CreditSights estimates for 2026. Ratios vary with revenue and capex assumptions and should be read as estimates.10

The gap between spending and revenue

In 2024 the investor David Cahn of Sequoia framed the central financial question of the build-out as a gap between the capital being deployed and the revenue required to justify it, an exercise widely known as the six hundred billion dollar question.12 The gap is real and worth watching. It is also narrowing, because AI revenue is growing quickly from a small base, in contrast to 2000, when the projected demand never showed up in the numbers at all.

The revenue is concentrated in a few providers and is growing fast, though the figures are self reported annualized run rates rather than audited results and should be read as such. OpenAI's run rate rose from roughly $200 million in early 2023 to about $13 billion in 2025 and toward an estimated $24 billion in early 2026. Anthropic reported a run rate of about $9 billion at the end of 2025 and roughly $30 billion by April 2026, a figure that is measured on a gross basis and is disputed by competitors.13

AI revenue run rate, leading providers
$ billions, log scale
Fast growth from a small base, unlike the absent demand of 2000.
Self reported annualized run rates, not audited revenue, and not directly comparable across companies because of differences in how sales are recognized. A logarithmic axis is used. Source. Company statements and reporting.13
Spending versus revenue, 2026 estimate
$ billions
The distance the revenue still has to travel to meet the spending.
Combined estimated platform capital spending against the combined run rate revenue of the leading AI providers. The gap is the substance of the so called six hundred billion dollar question. Figures are estimates.12

Depreciation, a shared question about earnings quality

The depreciation mechanism described in the telecom section applies here too, with one important difference. The useful life a company assigns to its servers and chips determines how quickly their cost runs through the income statement. Most large platforms depreciate this equipment over five to six years. Some investors, most prominently Michael Burry, have argued that the economic life of a leading chip is closer to two or three years, and estimated that the gap could understate depreciation across the group by around $176 billion between 2026 and 2028, overstating profit at some companies by twenty percent or more by 2028.14 Others counter that older chips remain useful for less demanding work and continue to earn, so the economic life is longer than the bears assume. The important points for a reader are that these are disclosed estimates rather than hidden facts, that reputable analysts disagree about the size of the effect, and that depreciation is a non cash charge, so it changes reported profit but not the cash already spent.

Chip economics, a much shorter asset life

This is where the comparison turns against the present cycle. Fiber, once laid, stayed useful for decades, which is why the surplus of 2000 was eventually absorbed at a profit by later users. The expensive hardware at the center of the AI build-out is different. Leading chips are refreshed on a roughly two year cadence, and the rental price of a prior generation chip falls quickly as a newer one arrives, by some estimates around 70% over the period since 2023. Because this hardware is the majority of the cost of a modern data center, while the building itself lasts far longer, the economics require continual reinvestment to stay current. That is a structurally different proposition from laying a cable that will still be valuable in twenty years.

Rental price of a leading chip over time
Approximate, per chip hour
Prices for a given generation fall sharply as the next arrives.
Illustrative path for a high end accelerator. The decline reflects newer hardware and added supply, and is the reason chip assets must be earned back quickly. Source. Industry trackers; figures are estimates.15

Circular financing, the same structure at larger scale

The vendor financing of 2000 has a direct descendant. Capital is again moving in loops among the companies that supply the build-out and the companies that buy from it. A chip maker invests in a model developer, which buys the chip maker's chips. A cloud provider funds a model developer, which runs on that provider's cloud. None of this is improper, and reputable reporting is careful to separate ordinary circular investment from the fraudulent round trip transactions of the past. The reason to watch it is the same as in 2000: when investment from a supplier returns as that supplier's revenue, the strength of underlying demand becomes harder to read from the headline numbers.

Chip makers
Supply accelerators, and invest in their buyers
Model labs
Buy chips and cloud capacity to train and serve models
Cloud providers
Fund labs and host them on their own infrastructure
Circular commitments, then and now
$ billions, log scale
The 2000 vendor loans alongside today's cross investments.
A logarithmic axis is used because the present commitments are far larger than the telecom era loans. Several current figures are ceilings or multi year commitments rather than cash deployed, and are labeled in the text.16

The specialized providers, the closest parallel to telecom debt

If a 2000 style strain were to appear, the most likely place is not the large platforms but the specialized providers that borrow to buy chips and rent them out, sometimes called neoclouds. CoreWeave is the clearest example, and it deserves an even handed reading because the outcome is genuinely unknown. On the cautious side, the company carried roughly $11 billion of debt in mid 2025, alongside about $34 billion of scheduled lease payments through 2028, its interest costs are large and rising, and in the second quarter of 2025 a single customer, Microsoft, accounted for about 71% of revenue, a concentration that turns one contract into an existential question.16 On the constructive side, revenue grew about 134% from a year earlier to roughly $1.4 billion in the third quarter of 2025, the company reported a contracted backlog above $55 billion, and it has the backing of Nvidia and offtake commitments from large, creditworthy customers. The structure, borrowing against fast depreciating assets with concentrated demand, is the one that failed in 2000. Whether the contracted backlog and strong sponsors make this time different is a real and open question, and no one can answer it with confidence today.

The takeaway

The large platforms have changed the funding model in a way that genuinely lowers systemic risk relative to 2000. At the same time, the assets wear out faster than fiber did, the spending still leads the revenue by a wide margin, and the older leveraged structure is reassembling itself among the specialized providers one level down. Those are observations to monitor, not predictions.

Part IV  ·  The New Constraint

Power and the grid, a limit that did not exist in 2000

Fiber used very little electricity. AI data centers use a great deal. The clearest difference between the two cycles is that the scarce input is no longer capital or even chips, but power and the equipment that delivers it. This is the part of the comparison with no real precedent, and it works both for and against the case that demand is durable.

US data centers used about 4.4% of the country's electricity in 2023, roughly 176 terawatt hours, up from under 2% only five years earlier. The Department of Energy and Lawrence Berkeley National Laboratory project that share rising to between 6.7 and 12% by 2028.20 Globally, the International Energy Agency estimates data center demand at about 415 terawatt hours in 2024 and projects it roughly doubling to around 945 terawatt hours by 2030, slightly more than Japan uses in a year.20 By the end of the decade the United States is on track to use more electricity for data centers than for the production of aluminum, steel, and cement combined.

US data center electricity use
Terawatt hours
A near tripling in a decade, with a wide range for 2028 that reflects real uncertainty.
Source. US Department of Energy and Lawrence Berkeley National Laboratory, 2024 data center energy report. The two 2028 figures show the low and high scenarios.20
Global data center electricity demand
Terawatt hours
The IEA base case, roughly doubling by 2030.
Source. International Energy Agency, Energy and AI. Data center demand reaches about 3% of global electricity by 2030 in the base case.20

The grid cannot keep pace

Demand is only half the story. The physical system cannot be expanded fast enough to meet it. At the end of 2023, about 2,600 gigawatts of proposed generation and storage were waiting in US interconnection queues, a figure that has since eased to roughly 2,060 gigawatts by the end of 2025, with typical waits of five years or more, and historically only around a tenth of queued capacity is ever built. The IEA estimates that roughly a fifth of planned data center projects worldwide face delays from grid connection alone. The equipment is its own bottleneck. The lead time for a large transformer has roughly doubled to about five years, and gas turbines, the usual fallback when the grid falls short, now carry delivery windows of five to seven years, with the leading manufacturer selling slots for 2030. Companies have responded by building their own generation on site rather than waiting in line.

Typical lead times for new supply
Years to deliver
Capital can be raised in days. None of these can.
Approximate current lead times. Sources. GE Vernova disclosures, IEA, and industry reporting. Figures are estimates and vary by project.

The turn to nuclear power

The clearest evidence that demand is real is what the companies are willing to commit to in order to secure power. After years of buying wind and solar credits, several have turned to nuclear for steady, around the clock supply, signing agreements that only make sense if the underlying compute demand is durable. Microsoft agreed a twenty year contract with Constellation to restart a unit at Three Mile Island, renamed the Crane Clean Energy Center, for 835 megawatts of dedicated power, with first power expected around 2027 to 2028 and a project cost of about $1.6 billion supported by a federal loan.17 Amazon paid $650 million for a campus beside the Susquehanna nuclear plant and invested a further $700 million in a small reactor developer. Google contracted for 500 megawatts from a small modular reactor developer. Across the industry, large technology companies have committed to roughly ten gigawatts of nuclear power in little more than a year.

Microsoft
835 MW
Three Mile Island restart with Constellation, a twenty year contract, about $1.6B to restart
First power ~2027 to 2028
Amazon
~960 MW
Susquehanna campus for $650M, plus $700M into a small reactor developer
2028 onward
Google
500 MW
First corporate small modular reactor agreement, with Kairos Power
2030 onward
Meta
up to 6.6 GW
The largest commitment, across several developers, on a longer timeline
2030s

A selection of roughly thirteen announced nuclear agreements totaling close to ten gigawatts. Sources. Company and Constellation announcements, Utility Dive, DCD.17

How US data centers are powered today
Approximate mix
Despite the nuclear agreements, natural gas supplies most current demand.
Source. International Energy Agency. Approximate current generation mix supplying US data centers; natural gas is also the largest single source of the near term increase.

Where this becomes a risk

The same facts that prove demand is real also create pressures that telecom never faced. In the regional grid known as PJM, which serves about 65 million people, the annual cost of the auction that keeps reserve power available rose from about $2.2 billion to $14.7 billion in a single year, and the grid operator's market monitor attributes roughly 40 to 45% of those costs to data center demand.18 Households across the region are being told to expect electricity bills 1.5 to 5% higher, and elected officials are looking for ways to shift the cost onto the companies driving it. A build-out that raises consumers' utility bills faces a political limit as well as a physical one. There is also the matter of idle capacity: a chip bought today begins losing value immediately, but if the power to run it is years away, much of that value is spent waiting.

176 TWh
US data center electricity in 2023, about 4.4% of the grid20
945 TWh
Projected global data center demand by 2030, near Japan's total20
2.6 TW
Generation waiting in US interconnection queues at the end of 2023
~11x
Rise in the PJM capacity price across two years18

The takeaway

Power is the practical limit on the pace of this cycle, and a genuinely new factor. The willingness to sign twenty year nuclear contracts is strong evidence that demand is real. The multi year waits for power, turbines, and transformers, together with rising consumer bills, are the clearest reasons the build-out could slow or cost more than planned. Both readings follow from the same data.

Part V  ·  The Financing

Private credit, special purpose vehicles, and leverage off the balance sheet

The statement that the large platforms fund their spending from cash flow is true, and a growing share of the build-out is nonetheless being financed in ways that do not appear on their balance sheets. That combination is the most precise parallel to 2000 in the whole comparison, and the one that is hardest to observe from the outside.

The template was set in October 2025, when Meta and Blue Owl Capital arranged about $30 billion of financing for a data center in Louisiana, the largest private capital transaction on record. Roughly $27 billion of debt and about $3 billion of equity sit in a separate vehicle. Meta owns 20% of that vehicle and outside investors own the rest, with large insurers and asset managers providing the debt. The bonds mature in 2049 and carry an investment grade rating. Meta develops, operates, and uses the site, but it is not the borrower, so the debt does not appear on Meta's balance sheet and its credit rating is unaffected.23 Oracle has used similar structures, building data centers through vehicles it then leases back.

This is a structural change in how the build-out is paid for, not a handful of deals. Data center related borrowing reached about $182 billion in 2025, roughly double the prior year, and large technology companies issued around $121 billion of corporate bonds, well above their recent average.21 Beneath the visible bond market, private credit lent to AI related companies has grown from almost nothing to more than $200 billion in a few years, and reputable estimates see it heading higher still over the rest of the decade.22

Data center related debt issuance
$ billions
A near doubling in a single year.
Data center related debt rose from about $92B in 2024 to about $182B in 2025. Source. S&P Global, with corporate bond issuance from market reporting. Figures are approximate.21
Selected off balance sheet and private credit deals
$ billions
A year earlier, a large data center financing was a few hundred million dollars.
A selection of recent vehicles and facilities. Sources. Bloomberg, Financial Times, and company disclosures.23

The layers, from steady to fragile

It helps to picture the build-out as layers of capital, from the cheapest and most transparent at the top to the most leveraged and least visible at the bottom. The risk is not at the top. It builds as you move down, and the lower layers increasingly resemble the structure that failed in 2000.

1. Operating cash flow
The majority of platform capital spending, funded from profitable businesses on net cash balance sheets. This is what most distinguishes the cycle from 2000.
Most of capex
2. Investment grade bonds
On the balance sheet, highly rated, and priced in public markets every day. Well understood and visible.
~$121B in 2025
3. Vehicles and private credit
Off the balance sheet, designed to protect credit ratings. Real leverage, funded by insurers and asset managers, and harder to see from outside.
~$182B issued, 2025
4. Specialized providers
Highly leveraged chip rental businesses with concentrated customers, borrowing against hardware that loses value quickly. The closest parallel to 2000.
Highest risk

Ordered from steadiest and most visible at the top to most leveraged and least visible at the bottom. The system's true leverage is the sum of all four layers, but only the top two are easy to read from published balance sheets.

Why it is reasonable, and why it is worth watching

There is a sound case that this is sensible financing rather than a warning sign. Long lived infrastructure is being funded by long duration capital, the insurers and pension funds behind the private credit managers, against multi year contracts with creditworthy tenants. Spreading the financing across the system is arguably healthier than concentrating it on a few balance sheets. The case for watching it closely is equally clear. Moving debt off the balance sheet means the true leverage of the build-out is understated by the headline figures, much as structured and vendor financing understated telecom's leverage a generation ago. The collateral inside these structures is not a long lived asset but hardware that ages in a few years. The arrangements are less liquid and less transparent than public markets, so strain can build quietly. And because insurers and pension funds hold much of the paper, the exposure reaches into the retirement and insurance systems. None of this is improper, and none of it is a problem today. It is the place where strain would be hardest to see in advance.

$30B
The largest private capital deal on record, Meta and Blue Owl23
$182B
Data center related debt issued in 2025, about double 202421
$200B+
Private credit already lent to AI related companies22
$120B+
Data center debt moved into off balance sheet vehicles23

The takeaway

The large platforms are in far stronger financial health than the telecom carriers ever were. At the same time, a growing share of the build-out is being financed through private credit and off balance sheet vehicles, secured against assets that age in a few years. That is worth following closely, precisely because it is the hardest part of the system to observe.

Part VI  ·  The Balanced Read

No single label fits

A careful comparison resists a one word answer. Sorted honestly, the evidence falls into four groups, and a complete picture holds all four at once.

Differences from 2000

Funding. The 2000 build-out was financed largely with debt, in the worst cases raised against fabricated earnings. This one is financed mainly from the profits of mature businesses, and most of the largest spenders carry more cash than debt. That balance sheet strength is the single clearest reason a debt driven, system wide failure is less likely this time.

Demand. The 2000 demand forecasts never appeared in revenue. Today AI usage is visible in reported revenue and in operating metrics, and the willingness to sign long dated power contracts is itself evidence that buyers expect the demand to last. Spending still leads revenue, but the revenue is real and growing.

Accounting. The defining failures of 2000 involved fraud. The depreciation debate today concerns disclosed estimates that reasonable analysts weigh differently. That is a difference in kind, and it shapes how any correction would unfold.

Asset life cuts the other way. Those three differences all reduce systemic risk relative to 2000. This one does not. Fiber laid in 2000 kept earning for decades, while the costly hardware in this build-out is refreshed every two to three years and is the majority of a data center's cost, so it must be earned back quickly. It is a real difference from the last cycle, and it adds pressure rather than easing it.

Where the cycles are similar

Capital intensity is higher now, both in dollars and relative to the size of the economy, though it is global and largely funded by cash flow, which softens the comparison even as the headline figure is larger.

Leverage is moving off the balance sheet, into private credit, special purpose vehicles, and the specialized providers. It is still modest against the cash and equity behind it, but it is growing quickly and gathering in the least visible layer.

Index concentration resembles the late 1990s and then exceeds it. The ten largest companies reached a record 40.7% of the S&P 500 in 2025, while generating about 32% of its earnings, so price has run ahead of profit at the top of the index.19

The genuine parallels

Circular financing is present again, at larger scale. The vendor loans of 2000 have a direct descendant in the cross investment among chip makers, model developers, and clouds, where capital can return as revenue and the true strength of demand is harder to read.

And the most important parallel, the leaders are not guaranteed. Even if AI proves as important as its advocates expect, the telecom precedent shows the original equity leaders can lag for a very long time while the technology succeeds. Nine of ten top names from 2000 trailed the index for 25 years.

The factor with no precedent

Power is the practical limit, and it is new. Fiber barely touched the grid. AI data centers are on track to use as much as 12% of US electricity by 2028, and the physical system cannot keep pace, with thousands of gigawatts waiting in queues and multi year waits for the equipment that moves power.

It supports both readings at once. Long dated nuclear and power agreements are strong evidence that demand is durable. At the same time, power scarcity introduces idle capacity, slipping schedules, and rising consumer bills that carry their own political limits. The same facts make demand more credible and the build-out more fragile.

The systemic risk of 2000 looks lower today. The risk of paying too much for the wrong leader looks similar. Both can be true at the same time, and an honest reading keeps them together. A balanced reading of the evidence

Part VII  ·  Things To Monitor

Signals worth watching

What follows is a set of observable indicators, not advice and not a forecast. Each is something a careful observer can track over time to see whether the dynamics described above are holding steady or shifting. The final item is a structural fact rather than a signal.

1   Earnings quality and cash flow

Because reported profit depends on depreciation assumptions, the cleaner figure to follow is cash. The spread between reported operating income and operating cash flow is a direct read on earnings quality, and persistent negative free cash flow funded by rising debt would mark a meaningful change from the current cash funded model.

2   The revenue gap

The distance between capital spending and AI revenue is the central financial question of the cycle. Whether that revenue keeps compounding toward the spending, or levels off, is observable each quarter, and it is the single clearest indicator of whether the build-out is being justified by demand.

3   Depreciation disclosures

The useful lives that companies assign to servers and chips appear in their filings. Further extensions of those lives would warrant attention, since they flatter near term profit, while shortenings would indicate that the faster replacement cycle is being recognized.

4   The financing layers

The growth and disclosure of off balance sheet vehicles and private credit financing can be tracked over time. The specific things to watch are how much leverage sits below the visible balance sheets, the customer concentration and debt levels at the specialized providers, and whether any vehicle is forced to mark down its hardware collateral.

5   Power and the grid

Power is now the difference between a data center that earns and one that sits idle. The observable signals are the gap between announced capacity and capacity actually energized, the clustering of project delays around grid constraints, and whether rising consumer electricity bills harden into cost shifting or limits on new connections.

6   Index concentration, a structural fact

This last point is not a signal to monitor but a present condition to understand. The ten largest companies are a record 40.7% of the S&P 500, which means a broad index fund now carries an unusually large exposure to the outcome of a handful of AI linked businesses.19 The base rate from 2000 is worth weighing: owning the largest, most celebrated names at peak valuations produced many years of underperformance even as the underlying technology reshaped the economy. Owning the technology and owning its current leaders remain two different things.

In closing

This note makes no call on what happens next. The evidence suggests the chance of a 2000 style downturn is lower, because the spending is funded differently, the demand is visible, and the accounting is disclosed rather than fabricated. The discipline that protected capital through the last cycle is still the relevant one: watch who is funding the spending, how quickly the assets age, whether the power exists to run them, and what price is being paid for any single leader. Those are the things worth keeping in view.

Data Reference

The AI economy, in thirty two panels

A reference appendix to the note above. Each panel states one figure, shows it simply, and cites its source in small print beneath. Figures are drawn from primary and reputable secondary sources and were checked in June 2026. Items that are estimates, projections, or drawn from a single research note are marked as such, in keeping with the educational aim of this document.

The macro and market picture
1
The Furman decomposition
Set aside technology and data center capital spending and the rest of the US economy grew at about 0.1% in the first half of 2025, annualized.
J. Furman, Harvard; BEA national accounts, Sept 2025. The 92% is the headline contribution; the net estimate reflects Furman's own qualification.
2
AI share of S&P 500 growth
single source
By several measures, AI linked companies account for roughly 75 to 90% of the index's recent growth.
JPMorgan, Michael Cembalest, 2026. A single research note; confirm against the original.
3
Returns by AI exposure
illustrative
Since late 2022, equity returns have spread widely depending on AI exposure.
FactSet; illustrative baskets, Nov 2022 to 2026. Baskets, not standard indices.
4
Largest single-day value losses
AI linked events now lead the record for single day market value losses. Nvidia, Jan 2025; Meta, Feb 2022; Apple, Sept 2020.
Bloomberg; market data. Meta's figure exceeds $232B.
Capability, adoption and cost
5
Frontier AI on hard benchmarks
~93%
On the hardest expert benchmarks, leading models now match or exceed specialists.
  • GPQA PhD science about 93%, versus about 70% for experts
  • FrontierMath about 25%; SWE-bench above 65%
Epoch AI; public benchmark leaderboards, early 2026. Scores move quickly.
6
How long a task AI can complete
The length of task a model can complete has roughly doubled every seven months, from seconds in 2020 toward many hours by 2026.
METR, Measuring AI Ability to Complete Long Tasks, 2025 to 2026.
7
Measured productivity gains
In randomized field studies, AI assistance raised output by 14 to 40%, with the largest gains in writing.
NBER 2023; BCG and Harvard 2023; MIT 2023.
8
Cost of quality-matched inference
The cost to reach a fixed quality level fell about 280 fold in roughly 18 months.
Stanford AI Index 2025; Epoch AI. Cost to query a fixed quality model.
9
Coding agent unit economics
illustrative
Illustrative daily cost of an AI agent versus the human equivalent, across several tasks.
Goldman Sachs, 2026. Illustrative figures from a single note.
10
AI's share of new code
~46%
On enabled accounts, AI can generate up to about 46% of code in controlled studies, with roughly 27 to 30% accepted.
GitHub; Google DORA research. Earlier 3% to 41% framing is not supported.
11
Frontier AI reaches a billion users
1B+
Combined users of leading AI products worldwide.
  • ChatGPT about 800M weekly active, from 100M in early 2023
  • Gemini about 750M monthly; reached 100M in two months
OpenAI; Alphabet Q4 2025 results; reporting. Mix of weekly and monthly measures.
12
Token volume toward 2030
projection
Projected monthly token volume rises sharply even as the cost per token falls.
Goldman Sachs, 2026. A forward projection, not a measured figure.
Jobs and capital flows
13
Software developer employment
US software developer employment has risen since 2019, to about 1.7 million in 2024, despite the replacement narrative.
BLS Occupational Employment and Wage Statistics, 2024. Broader definitions run higher.
14
Jobs that did not exist in 1940
60%
Share of 2018 US employment found in job titles that did not exist in 1940.
  • Software developer, data scientist, UX designer
  • Automation removes tasks and creates new roles
Autor, Chin, Salomons & Seegmiller, QJE 2024.
15
AI's share of venture capital
63%
Share of US venture dollars going to AI in 2025, up from roughly 12% in 2022.
  • OpenAI raised more than $40B across 2024 and 2025
  • Non AI early stage funding well below its 2022 peak
PitchBook, trailing twelve months, Q3 2025. The 2022 comparison is approximate.
16
Fastest revenue scaling on record
<2 yrs
Time for AI native companies to reach a billion dollars of annualized revenue.
  • OpenAI to about $13B run rate in roughly three years
  • Anthropic to about $9B by the end of 2025
Company disclosures; The Information. Self reported run rates.
The capital build-out
17
Hyperscaler capital spending
Combined spending by the four largest platforms is about 3.5 times its 2022 level, with no plateau yet.
Company filings; Epoch AI. Big four, excluding Oracle.
18
Capital spending versus past cycles
estimate
As a share of GDP, the AI build-out is meaningful but remains below the railroad era of the 1880s.
BEA; Goldman Sachs; historical reconstructions. Cross era figures have wide error bars.
19
Spending as a share of cash flow
94%
Hyperscaler capital spending now absorbs most operating cash flow, a high by recent standards.
Bank of America; Goldman Sachs. A point in time figure.
20
The useful-life debate
contested
5 to 6 yr
Booked life of five to six years against an estimated economic life of two to three.
  • One estimate puts understated depreciation near $176B for 2026 to 2028
  • The estimate is contested and unverified
M. Burry, 2025; Bank of America; company filings.
Credit and financing
21
AI related investment grade debt
projection
Issuance has grown sharply and is projected to keep rising toward the end of the decade.
Dealogic; Bloomberg; consensus estimates. The later years are a forecast.
22
Data center debt issued in 2025
$182B
Investment grade data center related issuance, roughly double the prior year.
  • Hyperscalers, REITs and private credit conduits
  • Largely funds chips and facilities
S&P Global, 2025, up from about $92B in 2024.
23
Data center debt, recent trend
Data center related issuance roughly doubled from 2024 to 2025.
S&P Global. Earlier eightfold framing against 2019 is not supported here.
24
Debt moved off the balance sheet
$120B+
Data center debt routed through special purpose vehicles.
  • Largest single deal about $30B, a private capital record
  • Rating agencies treat the vehicles as economic debt
Financial Times, December 2025.
25
Circular AI investment
Capital that loops between the companies supplying the build-out and the companies buying from it. The figures below are disclosed deals, and several are ceilings rather than cash committed.
  • Nvidia's pledge to OpenAI, up to $100B, a ceiling
  • Microsoft about $13B into OpenAI, which runs on Azure
  • Amazon $8B into Anthropic, which runs on AWS
Bloomberg; Financial Times; company filings. Reputable reporting separates circular investment from improper round trips.
26
Chip backed bond spreads
single source
Spreads on top rated chip backed paper tightened over roughly 18 months.
Specialized credit desk note. A single source; treat as indicative.
27
Technology credit spreads
point in time
~15 bp
Technology investment grade spreads sit modestly tighter than the broad index.
ICE BofA; Bloomberg indices. A point in time reading.
28
When a sector tops the credit market
directional
In past cycles, the point at which a single sector became the largest in the credit market tended to precede a widening in spreads.
  • Telecom, around 2000
  • Financials, around 2007
  • Energy, around 2014
Moody's; ICE BofA historical spreads. Directional; specific figures need a named series.
29
A split within software credit
specialized
+60 bp
Spreads on IT services have widened relative to AI infrastructure since 2023.
ICE BofA sub indices; Moody's. Specialized; confirm against the series.
30
Software credit maturities
estimate
Scheduled maturities for software and IT credit peak around 2028.
PitchBook; ICE BofA sub indices. Schedule is an estimate.
Power and the grid
31
Global data center electricity
Global data center demand is on track to roughly double by 2030, to about 945 terawatt hours.
International Energy Agency, Energy and AI, 2025.
32
AI demand reaches the grid
The PJM capacity price rose about elevenfold across two auctions, in dollars per megawatt day.
PJM Interconnection; Monitoring Analytics.